Schedule & Progress
• Phase 1 - commence 5th January 2009
• Phase 1 - completion 3rd September 2010 – complete refurbishment of Victorian building plus new build link block
• Phase 2 – commence 18th April 2010 – external playing facilities & landscape
• Phase 2 & Project completions 31st December 2010
• The current target programme indicates completion for Phase 1 as per the contract program but this incorporates the current delay of the science Block of two months.
Progress this month:
Refurbishment
- Continuation of works to last section of Donut / Science block.
Construction next month:
Refurbishment
- Continuation of all works to science block as per revised program & external works to main landscape areas.