Schedule & Progress
• Phase 1 - commenced 5th January 2009
• Phase 1 - completion 31st December 2010
• Phase 2 – commence 6th January 2011
• Phase 2 & Project completion 12th October 2011
• The current target programme is being progressed to complete Phase 1 works earlier than the contract and this will be reported on as the project progresses.
Progress this month:
- Continuation of all services at all zones
- Continuation of works to external works at South/ West / North elevation (excl soft)
- Completion to main roof finishes
- Internal progression for close out of drywall, joinery etc
Construction next month:
- Continuation of all service works to all zones for final fix & commissioning
- Continuation of works to external works at generally to Phase 1
- Continuation of final facade works (infill's etc)
- Continuation of fit out works to all zones including atrium works